2.14 MW ON LANDMARK'S WAREHOUSE (RDC) IN DUBAI SOUTH

In June 2018, SirajPower signed a new solar rooftop leasing contract with Landmark Group, one of the biggest multinational conglomerates and retailers in the region. Under this new partnership, SirajPower will carry out permitting, design, installation, commission and operation of Landmark Group's new solar system over a period of 20 years.


Location: Dubai South
System size: 2.14 MW
Roof Area: 22000 sq. m
Number of modules: 6282
Annual Energy Production: 3,500,000 kwh/year
Lease Duration: 20 years

1 MW ON AL ABBAR GROUP'S NEW STEEL AND ALUMINIUM FACILITY

In March 2018, SirajPower signed a solar rooftop contract with Al Abbar Aluminium, the leading family run GCC Facade company. SirajPower will deliver almost 1MW solar energy and help the company save nearly 40% of its expected consumption at its new steel and aluminium facility in Jebel Ali.


Location: Jebel Ali South
System size: 1MW
Roof Area: 9,100 sqm
Number of modules: 3,024
Annual Energy Production: 1,319
Lease Duration: 20 years
Completion Date: September 2018
img
img
img

RSA NATIONAL

Location: Dubai South
System size: 650kW
Roof Area: 10,000 sqm
Number of modules: 2,407
Annual Energy Production: 1,017
Lease Duration: 20 years
Completion Date: September 2018 

RSA Cold Chain

 
Location: Dubai South
System size: 800kW
Roof Area: 13,000 sqm
Number of modules: 2,750
Annual Energy Production: 1,300
Lease Duration: 20 years
Completion Date: May18 
img
img

Mochos


Location: Dubai Industrial City
System size: 214kW
Roof Area: 2500 sqm
Number of modules: 790
Annual Energy Production: 350,000 kwh
Lease Duration: 15 years
Completion Date: Oct 2018 

1 MW SOLAR SYSTEM ON HEPWORTH PME FACTORY ROOF

Hepworth is the Middle East premier manufacturer and supplier of plastic piping solutions. For their new factory in Dubai Investment Park, Hepworth decided to install solar panels on their factory roof.
 
Location: Dubai Investment Park (DIP), Dubai
System size: 1.04 MWp
Roof Area: 13,000 m2
Number of modules: 3,990
Annual Energy Production: 1.6 GWh/year
Lease Duration: 20 years
Completion Date: 2016 
img
img

400 KW ON THE NEW HEADQUARTER OF AXIOM TELECOM IN DUBAI SILICON OASIS

In May 2016, SirajPower and Axiom Telecom signed a 20-year lease agreement to deliver the first privately owned photovoltaic (PV) system in the Middle East. SirajPower will install the PV system at its own costs on Axiom Telecom’s roof and will be paid a monthly rent based upon the electricity produced by the system.

Location: Dubai Silicon Oasis, UAE
System size: 400 kWp
Roof Area: 3,800 m2
Number of modules: 1,500
Annual Energy Production: 638 MWh/year
Lease Duration: 20 years
Completion Date: 2016 

290 KW SOLAR SYSTEM ON EMIRATES TECHNOPACK FACTORY ROOF

Launched in 2003, Emirates Technopack is one of the leading flexible packaging companies in the UAE. Its manufacturing plant is equipped with the latest hi-tech machineries.
 
Location: Jebel Ali, Dubai
System size: 290 kWp
Roof Area: 3,000 m2
Number of modules: 1,092
Annual Energy Production: 541 MWh/year
Lease Duration: 20 years
Completion Date: 2016 
img
img

985 KWP SOLAR SYSTEM ON KANGAROO PLASTICS FACTORY ROOF

Launched in 1976, Kangaroo Plastics is one of the largest and most advanced integrated manufacturing plants in the Middle East. It is part of the Corys Packaging group.

Location: Jebel Ali Industrial Park
System size: 985 kWp
Roof Area: 12,900 m2
Number of modules: 3,720
Annual Energy Production: 1.6 GWh/year
Lease Duration: 20 years
Completion Date: 2017 